FORT ANN (V) WWTP

NPDES ID: NY0030627

S — SNC: Compliance schedule violation

The facility missed a deadline in its compliance schedule by more than 90 days.

This quarter: 5 effluent violations, 1 compliance schedule violation, 22 reporting violations.

Violations

April 30, 2026

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 45 mg/L (7 DA AVG)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (MO AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 30 mg/L (MO AVG)

DMR, Limited - Overdue

Nitrogen, ammonia total [as N]

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (DAILY MX)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (7 DA AVG)

DMR, Monitor Only - Overdue

Solids, suspended percent removal

0% over limit

Discharged 0 % against a permitted limit of 85 % (MO AV MN)

DMR, Limited - Overdue

Phosphorus, total [as P]

0% over limit

Discharged 0 kg/d against a permitted limit of 0.60381999 kg/d (ROLL AVG)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (7 DA AVG)

DMR, Monitor Only - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 30 mg/L (MO AVG)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (MO AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 18.61399984 kg/d (7 DA AVG)

DMR, Limited - Overdue

BOD, 5-day, percent removal

0% over limit

Discharged 0 % against a permitted limit of 85 % (MO AV MN)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 12.71199989 kg/d (MO AVG)

DMR, Limited - Overdue

Phosphorus, total [as P]

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (ROLL AVG)

DMR, Monitor Only - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (MO AVG)

DMR, Monitor Only - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 18.61399984 kg/d (7 DA AVG)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (7 DA AVG)

DMR, Monitor Only - Overdue

Flow, in conduit or thru treatment plant

118% over limit

Discharged 0.24 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 12.71199989 kg/d (MO AVG)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (7 DA AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 45 mg/L (7 DA AVG)

DMR, Limited - Overdue

Phosphorus, total [as P]

0% over limit

Discharged 0 mg/L against a permitted limit of 1 mg/L (MO AVG)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (MO AVG)

DMR, Monitor Only - Overdue

February 28, 2026

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (7 DA AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (7 DA AVG)

DMR, Monitor Only - Overdue

Nitrogen, ammonia total [as N]

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (DAILY MX)

DMR, Monitor Only - Overdue

Temperature, water deg. centigrade

0% over limit

Discharged 8 deg C against a permitted limit of 0 deg C (DAILY MX)

DMR, Monitor Only - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (MO AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 30 mg/L (MO AVG)

DMR, Limited - Overdue

Phosphorus, total [as P]

0% over limit

Discharged 0.1 mg/L against a permitted limit of 1 mg/L (MO AVG)

DMR, Limited - Overdue

pH

0% over limit

Discharged 0 SU against a permitted limit of 6 SU (MINIMUM)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (MO AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 45 mg/L (7 DA AVG)

DMR, Limited - Overdue

Flow, in conduit or thru treatment plant

0% over limit

Discharged 0 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Overdue

Solids, suspended percent removal

0% over limit

Discharged 96 % against a permitted limit of 85 % (MO AV MN)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 12.71199989 kg/d (MO AVG)

DMR, Limited - Overdue

pH

0% over limit

Discharged 0 SU against a permitted limit of 9 SU (MAXIMUM)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 30 mg/L (MO AVG)

DMR, Limited - Overdue

pH

0% over limit

Discharged 0 SU against a permitted limit of 0 SU (MAXIMUM)

DMR, Monitor Only - Overdue

Solids, settleable

0% over limit

Discharged 0 mg/L against a permitted limit of 0.0003 mg/L (DAILY MX)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 18.61399984 kg/d (7 DA AVG)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 18.61399984 kg/d (7 DA AVG)

DMR, Limited - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (MO AVG)

DMR, Monitor Only - Overdue

Phosphorus, total [as P]

0% over limit

Discharged 0.00454 kg/d against a permitted limit of 0.60381999 kg/d (ROLL AVG)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (7 DA AVG)

DMR, Monitor Only - Overdue

BOD, 5-day, percent removal

0% over limit

Discharged 93 % against a permitted limit of 85 % (MO AV MN)

DMR, Limited - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (MO AVG)

DMR, Monitor Only - Overdue

Solids, total suspended

0% over limit

Discharged 0 mg/L against a permitted limit of 45 mg/L (7 DA AVG)

DMR, Limited - Overdue

Phosphorus, total [as P]

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (ROLL AVG)

DMR, Monitor Only - Overdue

pH

0% over limit

Discharged 0 SU against a permitted limit of 0 SU (MINIMUM)

DMR, Monitor Only - Overdue

Solids, settleable

0% over limit

Discharged 0 mg/L against a permitted limit of 0 mg/L (DAILY MX)

DMR, Monitor Only - Overdue

BOD, 5-day, 20 deg. C

0% over limit

Discharged 0 kg/d against a permitted limit of 0 kg/d (7 DA AVG)

DMR, Monitor Only - Overdue

Solids, total suspended

0% over limit

Discharged 0 kg/d against a permitted limit of 12.71199989 kg/d (MO AVG)

DMR, Limited - Overdue

January 31, 2026

Flow, in conduit or thru treatment plant

145% over limit

Discharged 0.27 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

December 31, 2025

Flow, in conduit or thru treatment plant

127% over limit

Discharged 0.25 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

November 30, 2025

Flow, in conduit or thru treatment plant

127% over limit

Discharged 0.25 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

Phosphorus, total [as P]

34% over limit

Discharged 0.80811999 kg/d against a permitted limit of 0.60381999 kg/d (ROLL AVG)

DMR, Limited - Numeric Violation

August 31, 2025

Flow, in conduit or thru treatment plant

91% over limit

Discharged 0.21 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

Solids, suspended percent removal

47% over limit

Discharged 78 % against a permitted limit of 85 % (MO AV MN)

DMR, Limited - Numeric Violation

June 30, 2025

Flow, in conduit or thru treatment plant

91% over limit

Discharged 0.21 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

May 31, 2025

Flow, in conduit or thru treatment plant

136% over limit

Discharged 0.26 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

April 30, 2025

Flow, in conduit or thru treatment plant

136% over limit

Discharged 0.26 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

March 31, 2025

Flow, in conduit or thru treatment plant

136% over limit

Discharged 0.26 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

February 28, 2025

Flow, in conduit or thru treatment plant

27% over limit

Discharged 0.14 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

January 31, 2025

Flow, in conduit or thru treatment plant

91% over limit

Discharged 0.21 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

BOD, 5-day, 20 deg. C

2% over limit

Discharged 19.06799984 kg/d against a permitted limit of 18.61399984 kg/d (7 DA AVG)

DMR, Limited - Numeric Violation

BOD, 5-day, 20 deg. C

50% over limit

Discharged 19.06799984 kg/d against a permitted limit of 12.71199989 kg/d (MO AVG)

DMR, Limited - Numeric Violation

December 31, 2024

Flow, in conduit or thru treatment plant

82% over limit

Discharged 0.2 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

November 30, 2024

Flow, in conduit or thru treatment plant

36% over limit

Discharged 0.15 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

October 31, 2024

Flow, in conduit or thru treatment plant

27% over limit

Discharged 0.14 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

September 30, 2024

Phosphorus, total [as P]

103% over limit

Discharged 1.22579999 kg/d against a permitted limit of 0.60381999 kg/d (ROLL AVG)

DMR, Limited - Numeric Violation

Flow, in conduit or thru treatment plant

27% over limit

Discharged 0.14 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

August 31, 2024

Flow, in conduit or thru treatment plant

45% over limit

Discharged 0.16 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

July 31, 2024

Flow, in conduit or thru treatment plant

9% over limit

Discharged 0.12 MGD against a permitted limit of 0.11 MGD (MO AVG)

DMR, Limited - Numeric Violation

First flagged

April 14, 2026 (3 months ago)

Last confirmed

July 13, 2026 (25 days ago)